Question 46

To enable collaboration, the Product Owner, the Scrum Master, and the Scrum Team collaborate with each other and the stakeholders to create deliverables that provide the greatest possible value to the customer. This ensures realization of all the following project benefits, EXCEPT:

    Correct Answer: A

    The question is asking for the exception, which means the one option that is not a benefit of collaboration in Scrum. Option A describes efficient management of a large number of change requests, which is not a primary benefit of collaboration in Scrum. Collaboration in Scrum is more focused on continuous improvement, risk management, and team alignment, as described in options B, C, and D.

Discussion
Jozef_joeOption: A

A, SBOK - page 29, 2.5.1 Benefits of Collaboration in Scrum Projects