A planned failover of three VMs has just completed successfully, starting the VMs at the disaster recovery location. What next actions are available for the failover plan?

    Correct Answer: D

    After a planned failover of VMs has been completed successfully, typical available actions for the failover plan would include undoing the failover to revert the changes, starting the failover process again if needed, editing the failover plan for any necessary modifications, and deleting the plan if it is no longer needed. Therefore, the correct actions available would be Undo, Start, Edit, and Delete.

Discussion
Emmanski08Option: D

USED -Undo, Start, Edit, Delete

gaesOption: D

D is correct https://helpcenter.veeam.com/archive/backup/110/vsphere/failover_plan_undo.html

vCatOption: D

From Top: Start Start to... Undo Statistics Delete Edit...

MorkallOption: D

D is correct

nroyepicOption: D

Has to be D, Cancel doesn't exist as an entry

mstecnologiaOption: A