Exam OG0-093 All QuestionsBrowse all questions from this exam
Question 35

Which one of the following is responsible for the acceptance and sign-off of an Architecture Compliance review?

    Correct Answer: A

    The Architecture Board is responsible for the acceptance and sign-off of an Architecture Compliance review. This body plays a crucial role in ensuring that the architectural standards and regulations are being adhered to throughout the organization. The Architecture Board is typically composed of senior stakeholders and architects who are in charge of maintaining architectural governance and compliance.

Discussion
noureldinOption: A

Architecture Compliance Review Process Steps The main steps in the process are tabulated below:. 11 : Accept review and sign off : Architecture Board and Customer https://pubs.opengroup.org/architecture/togaf8-doc/arch/chap24.html

LillianXUEOption: A

42. Architecture Compliance 42.4.3 Steps No.11 Action: Accept review and sign off. Who: Architecture Board and Customer

BanzaaaiOption: A

A. Architecture Board

PrashanttheCloudMasterOption: A

Correct Answer 42.4.3 Steps Accept review and sign off. -----> Architecture Board and Customer