OG0-093 Exam - Question 4


Which phase of the ADM ensures that implementation projects conform to the defined architecture?

Show Answer
Correct Answer: D

Phase G: Implementation Governance is responsible for ensuring that implementation projects conform to the defined architecture. This phase provides oversight of the implementation process, ensuring adherence to the architectural vision and requirements. It involves managing and governing the implementation process to maintain alignment with the defined architecture.

Discussion

7 comments
Sign in to comment
AKYKOption: D
Aug 18, 2021

Correct Answer, Phase G is correct!

PrashanttheCloudMasterOption: D
Apr 19, 2022

Correct Answer, Phase G is correct!

NetRock1Option: D
Oct 26, 2020

Agree with the answer! Phase G is correct! The objective of Phase G are to: Ensure conformance with the defined architecture by implementation projects and other projects. https://pubs.opengroup.org/architecture/togaf8-doc/arch/chap13.html

KASPointOption: D
May 15, 2022

Conformance & Compliance Review is in Phase G.

[Removed]Option: D
Jun 1, 2022

Absolutely

noureldinOption: D
Oct 17, 2022

14.1 Objectives The objectives of Phase G are to: Ensure conformance with the Target Architecture by implementation projects Perform appropriate Architecture Governance functions for the solution and any implementation-driven architecture Change Requests. https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap14.html

MadboOption: D
Nov 29, 2023

D. Phase G: Implementation Governance Phase G focuses on providing an oversight of the implementation, ensuring that there is adherence to the defined architecture during the development and deployment of solutions. This phase involves managing and governing the implementation process, thus maintaining alignment with the architectural vision and requirements.