In which ADM Phase is the focus the creation of an Implementation and Migration Plan in co-operation with the portfolio and project managers?
In which ADM Phase is the focus the creation of an Implementation and Migration Plan in co-operation with the portfolio and project managers?
The Implementation and Migration Plan is a primary focus of Phase F in the Architecture Development Method (ADM). In this phase, the plan is created in co-operation with portfolio and project managers to ensure alignment with the overall enterprise strategy and change activities. While Phase E involves the initial creation of the Architecture Roadmap and an incomplete Implementation and Migration Plan, the detailed planning and coordination occur primarily in Phase F.
13.5:The focus of Phase F is the creation of an Implementation and Migration Plan in co-operation with the project and portfolio managers.
This is wrong. This is initially created in phase E then finalised in F. 12.3.11 Create the Architecture Roadmap & Implementation and Migration Plan
Yes. Answer B - Phase F 13.5 Approach The focus of Phase F is the creation of an Implementation and Migration Plan in co-operation with the project and portfolio managers. Phase E provides an incomplete Architecture Roadmap and Implementation and Migration Plan that address the Statement of Architecture Work. In Phase F this Roadmap and the Implementation and Migration Plan are integrated with the enterprise's other change activity.
Tricky one - documentation says it is created in E and F, but in which is it the *focus* - I would lean towards F...