OGEA-103 Exam QuestionsBrowse all questions from this exam

OGEA-103 Exam - Question 33


Consider the following statement.

According to the TOGAF standard, a governed approach of a particular deliverable will ensure adherence to the principles, standards, and requirements of the existing or developing architectures.

Which deliverable does this refer to?

Show Answer
Correct Answer: C

An Architecture Contract is the appropriate deliverable that ensures adherence to the principles, standards, and requirements of the existing or developing architectures. This formal agreement between stakeholders and the architecture team outlines the obligations, responsibilities, and deliverables, ensuring that the architecture development stays compliant with organizational standards and objectives.

Discussion

4 comments
Sign in to comment
thunderksOption: C
Dec 3, 2023

correct, the keyword is deliverable which in TOGAF sense is contract obligated documents

CyanideXOption: C
Dec 4, 2023

C is correct

bmdibrahimOption: C
Dec 17, 2023

Option C [VERIFIED] https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap32.html

aurableuOption: C
Feb 11, 2024

C is correct, https://pubs.opengroup.org/togaf-standard/architecture-content/chap04.html#tag_04_02_02:~:text=Adherence%20to%20the%20principles%2C%20standards%2C%20and%20requirements%20of%20the%20existing%20or%20developing%20architectures