Question 116

Which one of the following is responsible for the acceptance and sign-off of an Architecture Compliance review?

    Correct Answer: A

    The Architecture Board is responsible for the acceptance and sign-off of an Architecture Compliance review. This is consistent with the governance model where the Architecture Board oversees and ensures compliance with the architecture framework.

Discussion
rockyslavOption: A

https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap42.html 42.4.1 Overview The Architecture Compliance review process is illustrated in Figure 42-2 . Step 11 - "Accept review and sign off." Performed by "Architecture Board and Customer".

TeringzooiOption: A

Correct answer: A Step 11 - "Accept review and sign off." Performed by "Architecture Board and Customer". https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap42.html