Complete the sentence. A gap analysis will enable the architect to do all of the following except _____.
Complete the sentence. A gap analysis will enable the architect to do all of the following except _____.
A gap analysis will enable the architect to identify building blocks that have been inadvertently omitted, intentionally eliminated, to be carried over, or new building blocks that are needed. However, identifying potential vendors to provide new building blocks is not typically within the scope of a gap analysis. Gap analysis is focused on the evaluation of existing and required architectural components, rather than identifying external vendors.
Since Gap Ananlysis doesn't talk about vendors or stakeholders.
Activities Key activities in this step include: Create gap matrix as described under Approach, above. Identify building blocks to be carried over, classifying as either changed or unchanged. Identify eliminated building blocks. Identify new building blocks. Identify gaps and classify as those that should be developed, those that should be procured, and those inherited. https://pubs.opengroup.org/architecture/togaf80-doc/arch/p2/ta/ta_gapan.htm
Ans: B The technique known as gap analysis is widely used in the TOGAF Architecture Development Method (ADM) to validate an architecture that is being developed. The basic premise is to highlight a shortfall between the Baseline Architecture and the Target Architecture; that is, items that have been deliberately omitted, accidentally left out, or not yet defined. deliberately omitted!!
Correct Answer Check Chapter 23.2 Suggested Steps(TOGAF9.2)
https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap27.html Talks about all but there is no reference of vendor on this page
All the options seem to be right here, I am not sure why E was chosen as the Answer.