Exam OGEA-103 All QuestionsBrowse all questions from this exam
Question 65

What are the following activities part of?

• Risk classification

• Risk identification

• Initial risk assessment

    Correct Answer: B

    The activities listed—Risk classification, Risk identification, and Initial risk assessment—are all fundamental components of Risk Management. These activities aim to identify, evaluate, and prioritize risks to mitigate or manage their impact. These processes are essential for identifying potential risks and implementing measures to address them effectively.

Discussion
klezlilOption: B

https://pubs.opengroup.org/togaf-standard/adm-techniques/chap09.html#tag_09_04 The process for risk management is described in the following sections and consists of the following activities: Risk classification Risk identification Initial risk assessment Risk mitigation and residual risk assessment Risk monitoring