Exam OG0-092 All QuestionsBrowse all questions from this exam
Question 48

MightyGears produces components for the Car industry. Driven by the global financial downturn they are looking to reduce IT costs. They believe there is a cost saving opportunity within IT but this is not quantified in terms of potential savings nor is there an agreed target architecture. Final decisions on the solutions are not yet fully agreed. They have completed the first pass architecture and now are looking at the best opportunities and solutions to meet their financial goals.

You are the Chief Architect from a consulting organization brought into review the work to date by MightyGears and to make recommendations to the CIO and the board on the opportunities and solutions present.

Which of the following answers best describes how TOGAF recommends examining the opportunities and solutions before presenting to the board?

Choose one of the following answers

    Correct Answer: D

    The best practice according to TOGAF for examining opportunities and solutions before presenting to the board involves a comprehensive assessment. This includes understanding the corporate culture and attitude towards change, as well as constraints such as cost and time horizons. The architecture work must be reviewed for completeness, addressing any gaps, and ensuring all functional and interoperability requirements are met. Dependencies and risks should be validated, and an implementation and migration strategy formulated that identifies major work packages and transition architecture required. Finally, project charters should be created, and any changes from board discussions should be integrated into the architecture. This holistic approach ensures all aspects are covered, leading to an informed and strategic decision by the board.

Discussion
polymorfOption: D

Answer is D

Victor6510

Agree. Should be D.

EdgarrtOption: D

project charters is created after phase E, u need to approve plan first

bsiOption: D

I also believe that it should be D, but every site that has this question shows A. Does someone know officially what should be the answer?

el3ctronick

because all the sites have reproduced the work done by 1 person. they only stole the work done once. nobody cares if the answers are right, they don't validate them

sameersoftyhclOption: A

The question is examining the opportunities and solutions "before presenting to the board". Probably the last statement is option D was not needed. So I think A is the right answer.

sameersoftyhcl

D should be the right answer, because Project Charter is part of Phase F, should not be considered before approval from phase E

p_ze_wolfOption: D

D is exactly the content of the 12.3 chapter Steps of Phase E

mrg998

I say the answer is D also. D is the correct answer. This is the most complete description of the TOGAF approach to the Opportunities and Solutions phase this is specifically different from the other answers because it includes an assessment of the organisation. TOGAF refers to this as ‘Determine/confirm key corporate change attributes’ C is the second best answer, this misses out the assessment of key corporate change attributes. A is the third best answer because this misses out assessment of key corporate change attributes, and does not include the creation of portfolio and project charters and a retrospective update of the architectures. B is the red herring answer this is a description of the Migration phase in ADM.

el3ctronick

not exactly but looks the best against the rest available

Chang007Option: D

Answer is D; since the try to reduce the cost and option D talks about evaluation of Cost.

AJmanOption: D

The best Answer is D. A can be the second.

greenkarthik1Option: D

Answer D. The steps in Phase E are as follows: ■ Determine/confirm key corporate change attributes (see Section 12.3.1) ■ Determine business constraints for implementation (see Section 12.3.2) ■ Review and consolidate gap analysis results from Phases B to D (see Section 12.3.3) ■ Review consolidated requirements across related business functions (see Section 12.3.4) ■ Consolidate and reconcile interoperability requirements (see Section 12.3.5) ■ Refine and validate dependencies (see Section 12.3.6) ■ Confirm readiness and risk for business transformation (see Section 12.3.7) ■ Formulate Implementation and Migration Strategy (see Section 12.3.8) ■ Identify and group major work packages (see Section 12.3.9) ■ Identify Transition Architectures (see Section 12.3.10) ■ Create the Architecture Roadmap & Implementation and Migration Plan (see Section 12.3.11)

WatadOption: D

repeated, see Question #31, the answer was D in 31, hence should be D also here

Sasi2017Option: A

I am going with A as you have to assess the existing options in hand than reviewing the readiness for change. As that was done by the team already.

sanjepauOption: D

D should be the correct answer.

susrideyOption: D

A is migration planning talks about work packages and transition D is the right answer

pankaj3284Option: A

Answer is A , i will tell you why , question talks about oppurtunity and solution and not migration ..so it should not involve phase F steps

sameersoftyhcl

Project charter is part of Phase F

tushmish

Option A also has a reference to project charter '...and the project charters for the recommended projects for presentation to the board'