Question 120

Complete the sentence. The Requirements Management process is used to______.

    Correct Answer: C

    The Requirements Management process is used to organize architecture requirements throughout the ADM cycle. Its primary focus is on ensuring that any changes in requirements are identified, stored, and fed into the structure, maintaining an organized conduit for managing these requirements across all phases of the ADM.

Discussion
noureldinOption: C

Objectives To provide a process to manage architecture requirements throughout the phases of the ADM cycle Identify requirements for the enterprise, store them and feed them in and out of the relevant ADM phases, which dispose of, address and prioritize requirements http://www.togaf.com/admref/_chap15.html

LillianXUEOption: C

16. ADM Architecture Requirements Management This chapter looks at the process of managing architecture requirements throughout the ADM. 16.5 Approach 16.5.1 General Note also that the Requirements Management process itself does not dispose of, address, or prioritize any requirements; this is done within the relevant phase of the ADM. It is merely the process for managing requirements throughout the overall ADM.