Which of the following is an objective of ADM Phase G, Implementation Governance?
Which of the following is an objective of ADM Phase G, Implementation Governance?
An objective of ADM Phase G, Implementation Governance, is to ensure that implementation projects conform with the Target Architecture. This phase focuses on monitoring the implementation to ensure it aligns with the planned architecture, thereby maintaining governance over the process.
14.1 Objectives The objectives of Phase G are to: Ensure conformance with the Target Architecture by implementation projects Perform appropriate Architecture Governance functions for the solution and any implementation-driven architecture Change Requests. https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap14.html
Ensure conformance with the Target Architecture by implementation projects Perform appropriate Architecture Governance functions for the solution and any implementation-driven architecture Change Requests.
C. Ensure that implementation projects conform with the Target Architecture
Correct Answer 14.1 Objectives The objectives of Phase G are to: Ensure conformance with the Target Architecture by implementation projects Perform appropriate Architecture Governance functions for the solution and any implementation-driven architecture Change Requests