In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?
In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?
Phase F (Migration Planning) is the phase in the ADM where the Implementation and Migration Plan is coordinated with other frameworks. This phase focuses on creating a detailed implementation plan that aligns with other business frameworks and ensures that the architecture remains integrated with other planning and operational models.
Answer is C: Phase F https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap13.html The outcome of this step may well be that the Implementation and Migration Plan could be part of a different plan produced by another one of the frameworks with Enterprise Architecture participation.
The objectives of Phase E are to: 1. Generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D. 2. Determine whether an incremental approach is required, and if so identify Transition 3. Architectures that will deliver continuous business value. 3. Define the overall solution building blocks to finalize the Target Architecture based on the Architecture Building Blocks (ABBs). The steps in Phase E are as follows: 12.3.11 "Create the Architecture Roadmap & Implementation and Migration Plan". The Implementation and Migration Plan must demonstrate the activity necessary to realize the Architecture Roadmap. The Implementation and Migration Plan forms the basis of the migration planning in Phase F. The detail of the Implementation and Migration Plan, Version 0.1 must be aligned to the detail of the Architecture Roadmap and be sufficient to identify the necessary projects and resource requirements to realize the roadmap.