OG0-093 Exam QuestionsBrowse all questions from this exam

OG0-093 Exam - Question 87


In which ADM phase is the Implementation and Migration Plan coordinated with other frameworks?

Show Answer
Correct Answer: C

In Phase F of the Architecture Development Method (ADM), the Implementation and Migration Plan is coordinated with various management frameworks in use within the enterprise. This phase is focused on finalizing a detailed Implementation and Migration Plan, prioritizing work packages, and ensuring that all elements are aligned with the overall architectural vision and defined transition architectures.

Discussion

5 comments
Sign in to comment
noureldinOption: C
Nov 7, 2022

14.1 Objectives The objectives of Phase F are to finalize a detailed Implementation and Migration Plan; specifically: To ensure that the Implementation and Migration Plan is co-ordinated with the various management frameworks in use within the enterprise To prioritize all work packages, projects, and building blocks by assigning business value to each and conducting a cost/business analysis To finalize the Architecture Vision and Architecture Definition Documents, in line with the agreed implementation approach To confirm the Transition Architectures defined in Phase E with relevant stakeholders To create, evolve, and monitor the detailed Implementation and Migration Plan providing necessary resources to enable the realization of the Transition Architectures, as defined in Phase E https://pubs.opengroup.org/architecture/togaf90-doc/arch/chap14.html

gz11
Nov 2, 2021

This step is about coordinating the Implementation and Migration Plan with the management frameworks within the organization. https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap14.html

PrashanttheCloudMasterOption: B
Apr 22, 2022

Correct Answer 13.3.1 Confirm Management Framework Interactions for the Implementation and Migration Plan This step is about co-ordinating the Implementation and Migration Plan with the management frameworks within the organization. There are typically four management frameworks that have to work closely together for the Implementation and Migration Plan to succeed

BanzaaaiOption: C
Jul 29, 2022

with other frameworks

1learnerOption: C
Mar 19, 2024

Correct Answer - 'C' 13.3.1 Confirm Management Framework Interactions for the Implementation and Migration Plan This step is about co-ordinating the Implementation and Migration Plan with the management frameworks within the organization. There are typically four management frameworks that have to work closely together for the Implementation and Migration Plan to succeed: