According to TOGAF, in which phase of the ADM should an initial assessment of business transformation readiness occur?
According to TOGAF, in which phase of the ADM should an initial assessment of business transformation readiness occur?
According to TOGAF, an initial assessment of business transformation readiness should occur in Phase A. This phase is known as the Architecture Vision phase, where the preliminary phases set up the architecture capability, and Phase A is where the initial high-level work is conducted, including assessing the readiness of the organization for transformation.
6.3 Steps 6.3.5 Assess Readiness for Business Transformation A Business Transformation Readiness Assessment can be used to evaluate and quantify the organization's readiness to undergo a change. This assessment is based upon the determination and analysis/rating of a series of readiness factors, as described in 26. Business Transformation Readiness Assessment . The results of the readiness assessment should be added to the Capability Assessment (see Part IV, 32.2.10 Capability Assessment). These results are then used to shape the scope of the architecture, to identify activities required within the architecture project, and to identify risk areas to be addressed. https://pubs.opengroup.org/architecture/togaf9-doc/arch/chap06.html
Should be B https://pubs.opengroup.org/architecture/togaf91-doc/arch/chap30.html
as per 6.3.5 section in togaf standard version (Not pocket guide) the right answer is A
Correct Answer --- Phase A 6.3.5 Assess Readiness for Business Transformation A Business Transformation Readiness Assessment can be used to evaluate and quantify the organization's readiness to undergo a change. This assessment is based upon the determination and analysis/rating of a series of readiness factors, as described in 26. Business Transformation Readiness Assessment . The results of the readiness assessment should be added to the Capability Assessment (see Part IV, 32.2.10 Capability Assessment). These results are then used to shape the scope of the architecture, to identify activities required within the architecture project, and to identify risk areas to be addressed.