Question 14

Scenario:

Your role is consultant to the Lead Architect within a company that manufactures a variety of small electromechanical devices. The company is organized as independent operational divisions.

The company has a mature Enterprise Architecture practice and uses TOGAF standard for the basis of its architecture framework. In addition to the EA program, the company has a number of management frameworks in use, including business planning, portfolio/project management, and operations management. The EA program is sponsored by the CIO.

Each division has completed the Architecture Definition documentation required to tailor and configure the environment to meet its own specific manufacturing requirements.

The enterprise architects have analyzed the key corporate change attributes and implementation constraints. A consolidated gap analysis has been completed which has identified the gaps across the Business, Data, Application, and Technology domains. Based on the results of the gap analysis, the architects have reviewed the requirements, dependencies and interoperability requirements needed to integrate the new ERP environment into the existing environment. The architects have completed the Business Transformation Readiness Assessment started in Phase A. Based on all of these factors they have produced a risk assessment.

The implementation process is estimated to take four years. Because of the risks posed by the complexity of the current environment, a phased approach is needed to implement the target architectures. The implementation and Migration Plan v0 1, the draft Architecture Roadmap, and the Capability Assessment deliverables are now complete.

You have been asked to recommend the next steps to prepare the final Implementation and Migration Plan.

Based on TOGAF standard, which of the following is the best answer?

    Correct Answer: A

    To prepare the final Implementation and Migration Plan, it is crucial to prioritize the implementation projects and project increments based on their business value. The Business Value Assessment Technique should be applied to ensure that the projects with the highest return on investment are prioritized. This assessment will focus on performance evaluation criteria that can be used to monitor the progress of the architecture transformation. Subsequently, the Transition Architecture phases should be confirmed using an Architecture Definition Increments Table to list the projects. Documenting the lessons learned in this phase is also essential to ensure continuous improvement and to generate the final plan effectively.

Discussion
Divya07Option: B

B is correct Read the steps for Phase F,

Divya07Option: B

B is correct Read the steps for Phase F,

pankaj3284Option: B

Correct Answer is B , for sure Page 148 The focus of Phase F is the creation of an Implementation and Migration Plan in co-operation with the project and portfolio managers.

hou0220

Both A and B did not fully address the concerns. Option A missing coordination with other management frameworks to address "the company has a number of management frameworks in use.." Option B missing transition architectures to address "a phased approach is needed to implement the target architectures" I don't know which to choose!!

clementiOption: B

In my opinion B is more correct but also A is correct. Maybe with B you get 5 points and with A 3 points.

dassourav8903Option: B

B is correct

OPENSOFTOption: B

They say : "The implementation and Migration Plan v0.1, the draft Architecture Roadmap", version 0.1 of Implementation and Migration Plan, so you are in Phase E. Next is the first step of phase F. : "Confirm management framework interactions...". Answer B. is correct

faizy3Option: B

B looks good based on steps of phase F in the togaf doc

pankaj3284Option: B

B is Correct

CarlosPinheiroOption: B

I guess the available resources and priorities for the project are not taken into account when assigning a business value to projects (See 13.3.2 Assign a Business Value to Each in https://pubs.opengroup.org/architecture/togaf9-doc/arch/index.html). Thus, I believe A = 5 points and B = 3 points.

lxfmm

A or B? Hard to choose.

PratsMicOption: D

so you have initial implementation plan and you need final implementation plan and the whole initiative is going to take 5 years - wont you pick D ???- You would place the strategic Architecture Definition and Transition Architectures under configuration control as part of the ongoing architecture development cycle.

rkustagiOption: B

Follows Phase F steps

venksfcOption: A

A is correct due to BTRA

lorik75

In My Opinion, BTRA is not important, because the risks were already handled. The next point, why not A - Lessons learnt should be the last step. B ist the best choice.