Exam OG0-093 All QuestionsBrowse all questions from this exam
Question 116

According to TOGAF, which document should incorporate the actions arising from the Business Transformation Readiness Assessment technique?

    Correct Answer: D

    The Implementation and Migration Plan is the document that incorporates the actions arising from the Business Transformation Readiness Assessment technique according to TOGAF. This plan is developed during Phases E and F and addresses how to implement and migrate the architecture, including any necessary actions to ensure the organization is prepared for the transformation.

Discussion
noureldinOption: D

26.1 Introduction The recommended activities in an assessment of an organization's readiness to address business transformation are: Work these actions into Phase E and F Implementation and Migration Plan https://pubs.opengroup.org/architecture/togaf9-doc/m/chap26.html

LillianXUEOption: D

26. Business Transformation Readiness Assessment 26.1 Introduction Assess the risks for each readiness factor and identify improvement actions to mitigate the risk Work these actions into Phase E and F Implementation and Migration Plan

PrashanttheCloudMasterOption: D

Correct Answer 26. Business Transformation Readiness Assessment 26.1 Introduction Understanding the readiness of the organization to accept change, identifying the issues, and then dealing with them in the Implementation and Migration Plans is key to successful architecture transformation in Phases E and F. This will be a joint effort between corporate (especially human resources) staff, lines of business, and IT planners.