What document is sent from the sponsoring organization to the architecture organization to trigger the start of an ADM cycle?
What document is sent from the sponsoring organization to the architecture organization to trigger the start of an ADM cycle?
The document sent from the sponsoring organization to the architecture organization to trigger the start of an ADM cycle is the Request for Architecture Work. This document serves as an official request, initiating the architecture development process.
Correct answer: D https://pubs.opengroup.org/architecture/togaf90-doc/epf/TOGAF9/workproducts/Request%20for%20Architecture%20Work_6F6E672A.html
32.2.17 Request for Architecture Work Purpose This is a document that is sent from the sponsoring organization to the architecture organization to trigger the start of an architecture development cycle. Requests for Architecture Work can be created as an output of the Preliminary Phase, a result of approved architecture Change Requests, or terms of reference for architecture work originating from migration planning. In general, all the information in this document should be at a high level.
D Request for Architecture Work
32.2.17 Request for Architecture Work Purpose This is a document that is sent from the sponsoring organization to the architecture organization to trigger the start of an architecture development cycle. Requests for Architecture Work can be created as an output of the Preliminary Phase, a result of approved architecture Change Requests, or terms of reference for architecture work originating from migration planning. In general, all the information in this document should be at a high level.