OG0-092 Exam QuestionsBrowse all questions from this exam

OG0-092 Exam - Question 31


Scenario: AutoComp Corporation -

AutoComp Corporation produces components for the Car industry. Driven by the global financial downturn they are looking to reduce IT costs. They believe there is a cost saving opportunity within IT but this is not quantified in terms of potential savings nor is there agreed target architecture.

Final decisions on the solutions are not yet fully agreed. They have completed their Vision Phase and first pass of the three architecture definition phases and now they want to finalize and plan their solutions. You are the Chief Architect from a consulting organization brought into review the work to date by AutoComp

Corporation and to make recommendations to the CIO and the board on this.

Which of the following answers best describes how TOGAF recommends in this context?

Show Answer
Correct Answer: D

In this scenario, the primary focus is on finalizing and planning the solutions. According to TOGAF, after completing the Vision Phase and the first pass of the architecture definition phases, the next step is in Phase E, which involves Opportunities and Solutions. This phase includes reviewing the architecture work to ensure completeness, addressing any gaps, and then formulating implementation and migration strategies that identify major work packages and transition architectures. Finally, once an agreement is reached with the board, project charters are created, and any changes needed from the board discussions are factored into the architecture. This process aligns with the steps described in the chosen option.

Discussion

15 comments
Sign in to comment
polymorfOption: C
Sep 21, 2020

I would go with C

Prince_COption: C
Sep 19, 2020

C is the right answer

Victor6510
Sep 21, 2020

TOGAF recommends "Consolidated Gaps, Solutions, & Dependencies Matrix" for migration planning instead of "Consolidated Gap Analysis". Besides, Phase E contains other key steps instead of just focusing on the transition architecture.

mkngn208Option: D
Aug 31, 2022

Agree with D . Perfectly match the steps in phase E

dannysijiaOption: D
Oct 24, 2020

I will go for D

KMurthy04Option: D
Jul 28, 2021

I think its D, because the question asked was to "finalize and plan their solutions. " so we are in Phase F not E.that is why the cost factor.

Falconion
Mar 11, 2023

"finalize and plan their solutions" means, that the solutions are not yet decided on. this means, that the SBBs are not yet chosen. so we cannot be in phase F because the SBBs are selected in phase E.

EdgarrtOption: D
Mar 3, 2022

Cost is for phase F.

el3ctronick
Feb 27, 2024

from the framework phase E step 1 : Key steps in Phase E include: Identify Key Business Drivers Constraining Sequence of Implementation Examples are reduction of costs, consolidation of services, introduction of new customer services, etc.

mrg998Option: D
Jun 25, 2021

D is the best answer, addresses all the steps in Phase E.

AnilVOption: C
Jul 30, 2022

"They have completed their Vision Phase and first pass of the three architecture definition phases and now they want to finalize and plan their solutions." So next Phase is Phase E, where they do GAP analysis and then Migration & transition phases. it is more aligned to Answer "C".

Caren222Option: D
Nov 30, 2022

My only concern with D is why the Lead Architect creates the project charter. Is it role of the PM?

Red8aron
Jul 17, 2023

In the context of enterprise architecture and TOGAF, project charters are typically created by the organization's management or project sponsors. The project charter is a formal document that authorizes the existence of a project and provides the project manager with the authority to apply resources to project activities.

MzehkOption: D
Mar 25, 2021

D is correct, all the steps listed in Phase E

SixtyOption: B
Apr 6, 2021

I want to say B because it has the most steps from the Phase E 12.3.1 Determine/Confirm Key Corporate Change Attributes 12.3.2 Determine Business Constraints for Implementation 12.3.3 Review and Consolidate Gap Analysis Results from Phases B to D 12.3.4 Review Consolidated Requirements Across Related Business Functions 12.3.5 Consolidate and Reconcile Interoperability Requirements 12.3.6 Refine and Validate Dependencies 12.3.7 Confirm Readiness and Risk for Business Transformation 12.3.8 Formulate Implementation and Migration Strategy 12.3.9 Identify and Group Major Work Packages 12.3.10 Identify Transition Architectures 12.3.11 Create the Architecture Roadmap & Implementation and Migration Plan

Sixty
Apr 6, 2021

No I'm wrong D addresses more steps.

dave256
Sep 30, 2021

Yes D matches all these in Phase E

elainexsOption: A
Aug 3, 2022

Phase E, should be A.

KASTHUOption: C
Aug 15, 2022

Prilimnary, Phas A and first pass of BCD is complete and so the phase is E. C has steps from phase E

clementiOption: D
Mar 1, 2023

In this answer there are the steps of phase E

WatadOption: D
Mar 10, 2023

D is best, then B