In Which phase of the TOGAF ADM are Gap Analysis results from earlier phases consolidated?

Show Answer
Correct Answer: B

In TOGAF ADM, the Gap Analysis results from earlier phases are consolidated during Phase E. One of the objectives of Phase E is to generate the initial complete version of the Architecture Roadmap, based upon the gap analysis and candidate Architecture Roadmap components from Phases B, C, and D.