Exam ICGB All QuestionsBrowse all questions from this exam
Question 5

The use of Kanbans work best with pull systems for determining the timing of which products or services are produced.

    Correct Answer: A

    Kanban is a scheduling system for lean and just-in-time production, which inherently works best with pull systems. In a pull system, production is based on actual consumption rather than forecasted demand, and Kanbans are used to signal the need to move materials, objects, and parts through the production process. Therefore, the statement is true.

Discussion
AramadanOption: A

A. True