ICBB Exam QuestionsBrowse all questions from this exam

ICBB Exam - Question 65


Identify the correct option regarding PERT and CPM.

Show Answer
Correct Answer: BC

In CPM (Critical Path Method), the duration of each activity is known with certainty, whereas in PERT (Program Evaluation Review Technique), it assumes a probability distribution for the duration of each activity. This makes option B the correct choice as it accurately describes the key difference between the two project management techniques.

Discussion

1 comment
Sign in to comment
InvisibleBeing
Jun 7, 2023

I am confused!