Question 65

Identify the correct option regarding PERT and CPM.

    Correct Answer: B

    In CPM (Critical Path Method), the duration of each activity is known with certainty, whereas in PERT (Program Evaluation Review Technique), it assumes a probability distribution for the duration of each activity. This makes option B the correct choice as it accurately describes the key difference between the two project management techniques.