Question 2

Projects and which other artifact can be linked to either a program, a portfolio, both, or neither.

    Correct Answer: A

    Projects and demands can be linked to either a program, a portfolio, both, or neither. Demands often represent requests or needs that align with higher-level strategic goals, making them suitable for linkage to larger structures like programs and portfolios.

Discussion
netvision_gOption: A

Correct A.