Question 14

What is the default schedule for a project?

    Correct Answer: A

    The default schedule for a project is typically an 8-hour workday, and the most conventional distribution of these hours is from 8 AM to 12 PM and 1 PM to 5 PM with a one-hour lunch break in between. This aligns with traditional business hours.

Discussion
1307199725Option: A

Sorry , A is correct

BajelOption: A

https://docs.servicenow.com/bundle/utah-it-business-management/page/product/project-management/concept/project-management-intro.html

TonyWuYanDongOption: A

A is correct!

netvision_gOption: A

https://docs.servicenow.com/bundle/washingtondc-platform-administration/page/administer/time/reference/r_DefaultSchedules.html

1307199725Option: C

C is correct