Question 80

What is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting later?

    Correct Answer: D

    A baseline is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting later. It acts as a reference point to measure project performance and to assess any changes. It helps determine if the project is on track in terms of time, scope, and cost parameters.