What is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting later?
What is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting later?
A baseline is a data copy of the current project’s task, schedule, or structure that can be used for comparison reporting later. It acts as a reference point to measure project performance and to assess any changes. It helps determine if the project is on track in terms of time, scope, and cost parameters.
https://docs.servicenow.com/ja-JP/bundle/utah-it-business-management/page/product/project-management/task/compare-schedule-baselines-prj.html
D is correct
https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/project-management/task/compare-schedule-baselines-prj.html