Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
The property 'Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change' controls the changes in cost and resource plans with respect to the change in the start date of a demand or project. This property specifically addresses the relationship between the project start date and the associated plans, ensuring any alterations in the start date are reflected accordingly in the cost and resource plans.
A is correct
Note: The project property Change Resource Plan and Cost Plan Start Date with Demand or Project Start Date Change controls the changes in cost and resource plans with respect to the change in the start date of a demand or project. Source; https://docs.servicenow.com/bundle/washingtondc-it-business-management/page/product/project-management/task/change-planned-date-demand-project.html