Exam PSM II All QuestionsBrowse all questions from this exam
Question 57

Scrum has a role called `Project Manager.`

    Correct Answer: B

    Scrum does not include the role of `Project Manager`. Scrum identifies three specific roles: the Product Owner, the Scrum Master, and the Development Team. These roles are distinct and collectively ensure the success of the Scrum process.

Discussion
lenanguyen89Option: B

B is correct