PSM II Exam - Question 57


Scrum has a role called `Project Manager.`

Show Answer
Correct Answer: B

Scrum does not include the role of `Project Manager`. Scrum identifies three specific roles: the Product Owner, the Scrum Master, and the Development Team. These roles are distinct and collectively ensure the success of the Scrum process.

Discussion

1 comment
Sign in to comment
lenanguyen89Option: B
Jun 21, 2023

B is correct