Scrum has a role called `Project Manager.`
Scrum has a role called `Project Manager.`
Scrum does not include the role of `Project Manager`. Scrum identifies three specific roles: the Product Owner, the Scrum Master, and the Development Team. These roles are distinct and collectively ensure the success of the Scrum process.
B is correct