PSM I Exam - Question 163


When does a Sprint conclude? (Choose the best answer.)

Show Answer
Correct Answer: B

A Sprint in Scrum concludes when the Sprint Retrospective is complete. The Scrum framework consists of distinct events with specific purposes, and the Sprint Retrospective is the final event that takes place at the end of the Sprint. It is designed to reflect on the team's processes and to make improvements for the next Sprint. Therefore, the Sprint officially concludes with the completion of this event.

Discussion

3 comments
Sign in to comment
UppersquareCapitalOption: B
Sep 26, 2023

Correct Answer is B - When the Sprint Retrospective is complete. According to the Scrum Guide, A Sprint is timeboxed and is over whenever its timebox expires. The Sprint Retrospective is the final event of the Sprint, hence it concludes the Sprint.

Jyoti1010Option: B
Oct 3, 2023

When sprint retrospective is completed.

emelbaOption: B
Jan 8, 2024

When the timebox expires = When the Sprint Retrospective is complete.