Question 163

When does a Sprint conclude? (Choose the best answer.)

    Correct Answer: B

    A Sprint in Scrum concludes when the Sprint Retrospective is complete. The Scrum framework consists of distinct events with specific purposes, and the Sprint Retrospective is the final event that takes place at the end of the Sprint. It is designed to reflect on the team's processes and to make improvements for the next Sprint. Therefore, the Sprint officially concludes with the completion of this event.

Discussion
Jyoti1010Option: B

When sprint retrospective is completed.

UppersquareCapitalOption: B

Correct Answer is B - When the Sprint Retrospective is complete. According to the Scrum Guide, A Sprint is timeboxed and is over whenever its timebox expires. The Sprint Retrospective is the final event of the Sprint, hence it concludes the Sprint.

emelbaOption: B

When the timebox expires = When the Sprint Retrospective is complete.