PSM I Exam - Question 165


Which of these may a Scrum Team deliver at the end of a Sprint? (Choose the best answer.)

Show Answer
Correct Answer: D

A Scrum Team should deliver a valuable, useful increment that meets the Definition of Done at the end of a Sprint. This ensures that the increment is potentially shippable and provides value to stakeholders. Delivering an increment with minor known bugs, failing unit tests, or just a single document does not meet the standards of the Scrum framework.

Discussion

1 comment
Sign in to comment
Jyoti1010Option: D
Oct 16, 2023

D is correct.