PSM II Exam - Question 28


Doing your best and helping other Scrum Team members demonstrates which of the following?

Show Answer
Correct Answer: A

Doing your best and helping other Scrum Team members demonstrates the Value of Commitment. In Scrum, commitment is one of the core values, emphasizing that team members personally commit to achieving the team’s goals and supporting each other in that pursuit.