Question 148

Developers are self-managing, which of the following do they manage?

    Correct Answer: B

    Developers are responsible for managing the Sprint Backlog. The Sprint Backlog consists of the tasks and work items that the developers commit to completing in a Sprint. It is a plan created by the developers themselves which outlines what work will be done during the Sprint. This makes the management of the Sprint Backlog a core responsibility of developers, ensuring they have control over their workflow and can adjust as needed throughout the Sprint to meet their goals.

Discussion
AmrxOption: B

Sprint Lenght is decided by the Scrum Team.

DDSOption: B

'A' is correct : The Sprint Backlog is a plan by and for the Developers.

Jyoti1010Option: A

B is correct.