The Development Team can cancel the Sprint:
The Development Team can cancel the Sprint:
In Scrum, the Product Owner has the authority to cancel a Sprint. This decision might be made if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to make this decision; the Development Team does not have the authority to cancel a Sprint.
Answer is C