Question 58

A Scrum Team has been working on the same product for twelve Sprints. What would likely be the immediate impact on the original Scrum Team if two new

Scrum Teams are to be added the same product?

    Correct Answer: A

    The productivity of the original Scrum Team is likely to decrease because integrating new teams can introduce disruptions such as the need for onboarding, coordination, and communication with the new teams. These factors can divert the original team’s focus from their usual tasks and reduce their immediate productivity.

Discussion
amogOption: A

A is correct