Question 31

During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

    Correct Answer: B

    New work or further decomposition of work is added to the Sprint Backlog as soon as they are identified. This approach ensures that the team maintains transparency and flexibility throughout the Sprint, allowing the development team to adapt to new information and changes as quickly as possible.

Discussion
dipsMumbaiOption: B

Correct answer is B . Explanation is below . https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint

EmaEyeOption: D

I think that D is correct answer

Arend78Option: B

The question is about "work", not new backlog items/stories. As soon as there is a better understanding of what *work* actually needs to be done, this can/should be added to the Sprint backlog (transparency): https://scrumguides.org/scrum-guide.html#artifacts-sprintbacklog

AnosaOption: B

The Answer is B .. https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint

aam1972Option: B

First of all the responsible to make change on the sprint Backlog is the develop team. Second , develop team make a changes to the Backlog during the sprint "Work planned for the first days of the Sprint by the Development Team is decomposed by the end of this meeting, often to units of one day or less. The Development Team self-organizes to undertake the work in the Sprint Backlog, both during Sprint Planning and as needed throughout the Sprint." Conclusion : B: As soon as possible after they are identified.

Rz_rahgozarOption: A

How the correct answer can B as it is mentioned in Scrum Glossary " the Sprint Backlog is frozen " means that items (stories) in the Sprint Backlog cannot be added or removed during the Sprint. However it might be necessary to get more information, justify or clear some of the items during the Sprint, which should be done in he presence of the Product Owner.

okayheyOption: D

Gonna go against the grain and say D, since only the developers can change the sprint backlog. Any impediments are also raised during dailies and discussed with the team. No one person can make changes without discussing it as a team.

okayhey

Also since new work needs to be estimated first.

hiepnb97Option: B

B Sprint Backlog It is a highly visible, real-time picture of the work that the Developers plan to ...

DjedjigOption: B

B is correct

Jyoti1010Option: B

As soon as they are identified.

Jyoti1010Option: B

Option B .As soon as possible after they are identified.

GodfallOption: B

B. As soon as possible after they are identified. The Scrum Guide encourages that new work or further decomposition of work should be added to the Sprint Backlog as soon as it is identified to ensure transparency and flexibility during the Sprint.

Mi_WindsorOption: B

B is the correct answer