PSM I Exam - Question 31


During a Sprint, when is new work or further decomposition of work added to the Sprint Backlog?

Show Answer
Correct Answer: B

New work or further decomposition of work is added to the Sprint Backlog as soon as they are identified. This approach ensures that the team maintains transparency and flexibility throughout the Sprint, allowing the development team to adapt to new information and changes as quickly as possible.

Discussion

13 comments
Sign in to comment
dipsMumbaiOption: B
May 15, 2020

Correct answer is B . Explanation is below . https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint

EmaEyeOption: D
May 10, 2020

I think that D is correct answer

AnosaOption: B
May 28, 2020

The Answer is B .. https://www.scrum.org/forum/scrum-forum/5519/during-sprint-when-new-work-or-further-decomposition-work-added-sprint

Arend78Option: B
Jan 21, 2021

The question is about "work", not new backlog items/stories. As soon as there is a better understanding of what *work* actually needs to be done, this can/should be added to the Sprint backlog (transparency): https://scrumguides.org/scrum-guide.html#artifacts-sprintbacklog

Rz_rahgozarOption: A
Oct 30, 2020

How the correct answer can B as it is mentioned in Scrum Glossary " the Sprint Backlog is frozen " means that items (stories) in the Sprint Backlog cannot be added or removed during the Sprint. However it might be necessary to get more information, justify or clear some of the items during the Sprint, which should be done in he presence of the Product Owner.

aam1972Option: B
Apr 6, 2022

First of all the responsible to make change on the sprint Backlog is the develop team. Second , develop team make a changes to the Backlog during the sprint "Work planned for the first days of the Sprint by the Development Team is decomposed by the end of this meeting, often to units of one day or less. The Development Team self-organizes to undertake the work in the Sprint Backlog, both during Sprint Planning and as needed throughout the Sprint." Conclusion : B: As soon as possible after they are identified.

Mi_WindsorOption: B
Aug 25, 2023

B is the correct answer

GodfallOption: B
Sep 6, 2023

B. As soon as possible after they are identified. The Scrum Guide encourages that new work or further decomposition of work should be added to the Sprint Backlog as soon as it is identified to ensure transparency and flexibility during the Sprint.

Jyoti1010Option: B
Sep 26, 2023

Option B .As soon as possible after they are identified.

Jyoti1010Option: B
Sep 26, 2023

As soon as they are identified.

DjedjigOption: B
Feb 19, 2024

B is correct

hiepnb97Option: B
Mar 3, 2024

B Sprint Backlog It is a highly visible, real-time picture of the work that the Developers plan to ...

okayheyOption: D
Mar 29, 2024

Gonna go against the grain and say D, since only the developers can change the sprint backlog. Any impediments are also raised during dailies and discussed with the team. No one person can make changes without discussing it as a team.

okayhey
Mar 29, 2024

Also since new work needs to be estimated first.