PSM I Exam - Question 23


Which outcome is expected as Scrum Teams mature?

Show Answer
Correct Answer: A

As Scrum Teams mature, they strive to continuously improve their processes and practices. One important aspect of this improvement is refining their definition of 'Done' to include more stringent criteria. This ensures that the quality of their deliverables remains high and that they are meeting increasingly higher standards over time. Such maturation reflects a growing understanding of the product, the technology, and the users' needs.