Question 27

For which is the Scrum Master responsible?

    Correct Answer: C

    The Scrum Master is responsible for ensuring that the Scrum framework is being adopted and used properly. This includes facilitating Scrum events, coaching the team on Scrum practices, and helping to remove impediments to the team's progress. Managing the performance of the team, setting meetings and objectives, or keeping track of resource allocation are not primary responsibilities of the Scrum Master.

Discussion
Naz1Option: C

C. The Scrum framework being adopted and used properly.

VaheDAOption: C

C. The Scrum framework being adopted and used properly.

maverick_walkerOption: C

C is correct

okayheyOption: C

C is correct

hiepnb97Option: C

C is correct

DjedjigOption: A

A is correct

Jyoti1010Option: C

Option C is correct.

Mi_WindsorOption: C

C is the correct answer