Question 26

Stakeholders are only allowed to meet with the Scrum Team at Sprint Review.

    Correct Answer: B

    Stakeholders are not limited to meeting with the Scrum Team only during the Sprint Review. While the Sprint Review is an important event for stakeholders to provide feedback, stakeholders can also engage with the Scrum Team during other events such as Product Backlog Refinement and Sprint Planning, or even during the Sprint if necessary. Hence, the statement is false.

Discussion
lenanguyen89Option: B

B is correct

amogOption: B

B is correct

avkOption: A

The stake holder will meet the whole scrum team only in scrum Review. So the answer will be A, Exam team kinldy clarify.

Edgecrusher77Option: A

Correct answer is A And explanation is about A

Mi_WindsorOption: B

B is the correct answer