PSM II Exam - Question 112


Which of the following actions is appropriate for a Scrum Master at the Daily Scrum?

Show Answer
Correct Answer: C

The appropriate action for a Scrum Master at the Daily Scrum is teaching the Development Team to keep the Daily Scrum time-boxed to 15 minutes or less. The Scrum Master is responsible for ensuring that all Scrum events occur and are positive and productive. The Daily Scrum is a meeting for the Development Team and not led directly by the Scrum Master. It is crucial for the event to be time-boxed efficiently, and it is the Scrum Master’s role to guide and educate the team in adhering to Scrum practices, including time-boxing.

Discussion

1 comment
Sign in to comment
amogOption: C
Mar 10, 2021

C is correct