Question 4

How should a Development Team deal with non-functional requirements?

    Correct Answer: A

    A Development Team should ensure every Increment meets non-functional requirements. Non-functional requirements are part of the Definition of Done, meaning each increment must adhere to these standards to be considered complete and releasable. This ensures a consistent level of quality and performance across all increments.

Discussion
Naz1Option: A

A - Ensure every Increment meets them

Jyoti1010Option: A

Non functional requirements are added to Definition of Done and each increment needs to adhere it.

okayheyOption: A

Correct

DjedjigOption: A

A is correct

rdftu12_1

We can update the question. Scrum guide 2020 talk about developers and not developement team.

Ravindra77Option: D

answer is D, sprint will be ended when the time box expires irrespective of its increment.