How should a Development Team deal with non-functional requirements?
How should a Development Team deal with non-functional requirements?
A Development Team should ensure every Increment meets non-functional requirements. Non-functional requirements are part of the Definition of Done, meaning each increment must adhere to these standards to be considered complete and releasable. This ensures a consistent level of quality and performance across all increments.
A - Ensure every Increment meets them
Non functional requirements are added to Definition of Done and each increment needs to adhere it.
Correct
A is correct
We can update the question. Scrum guide 2020 talk about developers and not developement team.
answer is D, sprint will be ended when the time box expires irrespective of its increment.