PSM I Exam - Question 4


How should a Development Team deal with non-functional requirements?

Show Answer
Correct Answer: A

A Development Team should ensure every Increment meets non-functional requirements. Non-functional requirements are part of the Definition of Done, meaning each increment must adhere to these standards to be considered complete and releasable. This ensures a consistent level of quality and performance across all increments.

Discussion

6 comments
Sign in to comment
Naz1Option: A
Dec 31, 2020

A - Ensure every Increment meets them

Jyoti1010Option: A
Sep 26, 2023

Non functional requirements are added to Definition of Done and each increment needs to adhere it.

Ravindra77Option: D
Jul 18, 2023

answer is D, sprint will be ended when the time box expires irrespective of its increment.

rdftu12_1
Oct 25, 2023

We can update the question. Scrum guide 2020 talk about developers and not developement team.

DjedjigOption: A
Feb 19, 2024

A is correct

okayheyOption: A
Mar 29, 2024

Correct