PSM I Exam - Question 4


How should a Development Team deal with non-functional requirements?

Show Answer
Correct Answer: A

A Development Team should ensure every Increment meets non-functional requirements. Non-functional requirements are part of the Definition of Done, meaning each increment must adhere to these standards to be considered complete and releasable. This ensures a consistent level of quality and performance across all increments.

Discussion

7 comments
Sign in to comment
Naz1
Jun 30, 2021

A - Ensure every Increment meets them

Jyoti1010
Mar 26, 2024

Non functional requirements are added to Definition of Done and each increment needs to adhere it.

Ravindra77
Jan 18, 2024

answer is D, sprint will be ended when the time box expires irrespective of its increment.

rdftu12_1
Apr 25, 2024

We can update the question. Scrum guide 2020 talk about developers and not developement team.

Djedjig
Aug 19, 2024

A is correct

okayheyOption: A
Sep 29, 2024

Correct

yugdevOption: A
Feb 15, 2025

A : non-functional requirements are equally imp hence needs to be taken care of before hand & not at the end.