Question 81

In what ways does the Scrum Master keep a Development Team working at its highest level of productivity?

    Correct Answer: A

    The Scrum Master helps the Development Team maintain its productivity primarily by removing impediments that hinder progress and by facilitating team decisions. This ensures that the Development Team can focus on their work without unnecessary disruptions. The Scrum Master's role is to support and enable the team, rather than directly participate in activities like user acceptance tests or tracking defects.

Discussion
nhungnt184Option: A

A is correct.

amogOption: A

Answer is A