Exam PSM II All QuestionsBrowse all questions from this exam
Question 29

Peter, a Project Manager, has raised concerns about your Scrum Team's productivity and progress towards the objectives.

Which is the best way to respond to Peter's concerns?

    Correct Answer: A

    The best way to respond to Peter's concerns about the Scrum Team's productivity and progress is by sharing the Product Backlog, the projections towards the release dates, and ensuring that Peter has access. This approach provides transparency, which is a fundamental principle of Scrum. It allows Peter to see the work that has been planned, the progress being made, and how it aligns with the release objectives. This information helps manage expectations and facilitates better communication and collaboration between the team and stakeholders.

Discussion
nhungnt184Option: C

Why not C?

stealthelephant

Because the developers are responsible for managing sprint impediments and in the review they will cover their progress.

amogOption: A

Should be A

Mi_WindsorOption: A

A is the correct answer