PSM I Exam - Question 24


When must a Scrum Team release each Increment?

Show Answer
Correct Answer: A

In Scrum, an increment should be released when it makes sense to release it. The Product Owner, who is responsible for maximizing the product's value, makes the decision based on various factors, including business value and customer needs. While increments must be 'Done' by the end of each Sprint and be potentially releasable, they do not have to be released immediately. This approach allows for flexibility in releasing only when it brings the most value.

Discussion

11 comments
Sign in to comment
CliuOption: A
Sep 7, 2023

Increment should be releasable, but not necessarily to be released

Jyoti1010Option: A
Sep 26, 2023

Scrum team can decide when to release an increment.They not necessarily need to wait for review.The moment any sprint backlog item conform the Definition of Done , a new increment is born.

LuchitoOption: D
Jun 28, 2023

According to the Scrum Guide, each increment must be released at the end of each Sprint, regardless of whether or not it is shipped to customers.

Marty10
Aug 12, 2023

So then it can't be released AFTER the sprint I think?!

amit_swolf
Aug 28, 2023

this is google's top result but its incorrect. when product backlog item reaches DoD, it can be released at any point. A is correct

293ebceOption: A
Aug 13, 2023

Correct Answer is A. During the Sprint Product Backlog Item(s) turn into Increment(s). They meet the definition of "Done". An Increment can be released now, or later - at any given time. Releasing means putting value in the hands of customers.

GodfallOption: A
Sep 6, 2023

Based on the Scrum Guide, the answer to the question "When must a Scrum Team release each Increment?" is: A. When it makes sense to release it. Scrum Teams are encouraged to release increments of the product as soon as it makes sense to do so, based on their product's goals and customer needs. There is no strict requirement to release after every Sprint, and it should be driven by the business value and timing considerations rather than being tied to a fixed schedule.

RamanAgarwalOption: D
Jun 14, 2023

Correct Answer is Option D. We should release the increment at the end of every sprint. Doesnt need to go to production

JoshyKawasaki
Jun 28, 2023

Answer is A. Ultimate goal of each sprint is to produce an increment of value. PO makes the decision as to if/when it is released. It is not a mandatory requirement at the end of each sprint.

Issam_KHELILOption: A
Oct 18, 2023

Answer A is correct

DjedjigOption: A
Feb 19, 2024

A is correct

MarcoScaramelliOption: D
Feb 21, 2024

Answer is D, an increment must be released at the end of each sprint. Then it can be delivered to users/market when the prod owner decides that it makes sense.

okayhey
Mar 27, 2024

No it doesn't, it just needs to meet the definition of done. It's up to the PO to release it or not. An increment is a POTENTIALLY releasable piece of software.

okayheyOption: A
Mar 29, 2024

A is without a doubt correct

maverick_walkerOption: A
Apr 29, 2024

A is correct