A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments.
Which would be the LEAST helpful technique in this situation?
A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments.
Which would be the LEAST helpful technique in this situation?
Scrum does not include the role of a project manager, and arranging a triage meeting with project managers would not be a practical or effective approach to resolving impediments in a Scrum framework. Instead, techniques that align more closely with Scrum principles, such as consulting with the Development Team, prioritizing the impediments, or alerting management about their impact, are more appropriate and helpful in this situation.
C is the correct answer because it is a LEAST
C is the answer