Exam PSM I All QuestionsBrowse all questions from this exam
Question 34

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

    Correct Answer: B

    When multiple Scrum Teams work from the same Product Backlog, the Development Teams pull in work in agreement with the Product Owner. This ensures that the Product Backlog items are chosen based on priority and relevance to the product goals, as determined by the Product Owner, while allowing each team to manage their own capacity and commitments.

Discussion
nhungnt184Option: B

Cannot be C because there is only ONE product backlog in Scrum framework (even in Scrum of Scrums). B is the best option.

Edgecrusher77Option: B

It cant be C, only 1 Product backlog is possible per product. But you can have several Sprint backlogs, one per team. Correct answer is B

babybabyOption: B

The ansswer is B, 1 product= 1 product backlog=1 product owner

maverick_walkerOption: B

B is correct

DjedjigOption: B

B is correct

DipakKateOption: B

Option B

Jyoti1010Option: B

Option B is correct.Developers in collaboration with product owner will decide.

amit_swolfOption: B

Single team or multiple, its development team responsibility to choose the work

Mi_WindsorOption: B

B is the correct answer

VaheDAOption: B

C is NOT the answer FOR SURE

AnsarfoolchandOption: C

Ansar is C. Each team should have its own backlog.

Mi001

There is a single product backlog, I doubt you are right

scrumk

your answer is unethical in scrum as they must all have same product backlog

Tianee

Team may have its own sprint backlog, but product backlog should always be just one.