PSM I Exam QuestionsBrowse all questions from this exam

PSM I Exam - Question 34


How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

Show Answer
Correct Answer: B

When multiple Scrum Teams work from the same Product Backlog, the Development Teams pull in work in agreement with the Product Owner. This ensures that the Product Backlog items are chosen based on priority and relevance to the product goals, as determined by the Product Owner, while allowing each team to manage their own capacity and commitments.

Discussion

11 comments
Sign in to comment
babybabyOption: B
Nov 20, 2020

The ansswer is B, 1 product= 1 product backlog=1 product owner

Edgecrusher77Option: B
Dec 7, 2020

It cant be C, only 1 Product backlog is possible per product. But you can have several Sprint backlogs, one per team. Correct answer is B

nhungnt184Option: B
Dec 29, 2020

Cannot be C because there is only ONE product backlog in Scrum framework (even in Scrum of Scrums). B is the best option.

AnsarfoolchandOption: C
Nov 9, 2020

Ansar is C. Each team should have its own backlog.

Mi001
Jan 3, 2021

There is a single product backlog, I doubt you are right

scrumk
Feb 25, 2021

your answer is unethical in scrum as they must all have same product backlog

Tianee
Apr 24, 2021

Team may have its own sprint backlog, but product backlog should always be just one.

VaheDAOption: B
Jan 7, 2021

C is NOT the answer FOR SURE

Mi_WindsorOption: B
Aug 10, 2023

B is the correct answer

amit_swolfOption: B
Aug 28, 2023

Single team or multiple, its development team responsibility to choose the work

Jyoti1010Option: B
Sep 26, 2023

Option B is correct.Developers in collaboration with product owner will decide.

DipakKateOption: B
Nov 1, 2023

Option B

DjedjigOption: B
Feb 19, 2024

B is correct

maverick_walkerOption: B
Apr 29, 2024

B is correct