Scrum is based on which of the following?
Scrum is based on which of the following?
Scrum is based on empiricism. Empiricism means working in a fact-based, experience-based, and evidence-based manner. In Scrum, decisions are made based on what is known and what has been observed. This approach is essential for dealing with complex problems and unpredictable environments, as it allows for continuous learning and adaptation.
C is correct
C is correct
C is the correct answer