PSM I Exam - Question 40


Which Scrum Values are exhibited by not building Product Backlog items that have low business value? (Choose three.)

Show Answer
Correct Answer: BCE

In Scrum, certain values guide the actions and decisions of the team. Not building Product Backlog items that have low business value exhibits several of these values. Respect is shown by acknowledging the importance of the team's and stakeholders' time and effort, thereby ensuring that effort is spent on valuable work. Focus is demonstrated by prioritizing high-value items and maintaining an effective direction towards delivering the most valuable features. Courage is required to make difficult decisions, including the decision to say no to low-value work despite any potential pressures to include it. Therefore, the values exhibited in this scenario are Respect, Focus, and Courage.

Discussion

8 comments
Sign in to comment
PSMhelp
Feb 29, 2020

This question was on the exam

GodfallOptions: BCE
Sep 6, 2023

In the Scrum Guide, the Scrum Values are defined as: Commitment Courage Focus Openness Respect So, let's evaluate which Scrum Values are exhibited by not building Product Backlog items that have low business value: B. Respect: By not building low-value items, you are showing respect for the team's time and effort as well as for the stakeholders' resources. C. Focus: Choosing not to build low-value items demonstrates a focus on delivering high-value items and prioritizing work effectively. E. Courage: It takes courage to make decisions about what not to build, especially if there is pressure to do everything. It shows courage to say no to low-value work. So, the correct answers to your question are B, C, and E.

monibunOptions: ACD
Sep 23, 2020

what does respect and courage has to do with it ?

Swekkel22
Sep 24, 2020

the DT shows courage to discuss with PO and choose to disregard a functionality, and the team members respect that the decision is made

TianeeOptions: BCE
Apr 24, 2021

B, C, E are the only choices as the other two are NOT any of the 5 Scrum value...

Arend78
Jan 22, 2021

I guess the other 2 answers are not Scrum values. I have seen in other questions that "all scrum values are impacted" if scrum is not executed correctly.

Anjani2020Options: BCE
Feb 6, 2021

I think, correct answer should be only focus ( to deliver product with maximize value) and courage (courage to stop low output). In question it's mentioned to select 3, no other option better than selecting respect .

Mi_WindsorOptions: BCE
Aug 25, 2023

BCE is the correct answer

Jyoti1010Options: BCE
Sep 26, 2023

Option B C and E