When is it most appropriate for a Development Team to change the definition of `Done`?
When is it most appropriate for a Development Team to change the definition of `Done`?
The most appropriate time for a Development Team to change the definition of 'Done' is during the Sprint Retrospective. The Sprint Retrospective is a meeting where the team reflects on the past Sprint and identifies ways to improve. It is a suitable time to modify the definition of 'Done' because the team can assess what worked well and what didn’t, and then update their processes and standards accordingly to enhance future Sprints.
The correct answer is C. During the Sprint Retrospective. Explanation: The Sprint Retrospective is the most appropriate time for the Development Team to reflect on their practices and processes. If the Development Team identifies opportunities for improvement or finds that the current Definition of Done is inadequate, they can propose changes to it during the Sprint Retrospective. This allows the team to continuously enhance their Definition of Done, align it with their evolving understanding and requirements, and ensure it effectively reflects the expected quality and completeness of their work. It is a valuable opportunity to refine and update the Definition of Done for future Sprints.
During sprint retrospective Definition of done can be modified as we know more about the product and non functional requirements.
C is correct
C during the spring retrospective