Question 73

How is management external to the Scrum Team involved in the Daily Scrum?

    Correct Answer: B

    The Daily Scrum is an event in the Scrum framework that is meant primarily for the development team to discuss their progress towards the Sprint Goal and plan their work for the next 24 hours. Management is not required to attend the Daily Scrum. Its purpose is to allow the developers to quickly and effectively synchronize their activities and create a plan for the day. The involvement of management in this meeting would bypass the self-organizing nature of the Scrum team.

Discussion
Jyoti1010Option: B

Daily scrum is attended by the developers only.

Mi_Windsor

Why not D? Please explain

yasir_34z

The question focuses on Daily Scrum, and Product Owner is a representative of the management but he is not required to attend Daily Scrum.

ceausorinOption: D

Why not D?

ficklesena

Product Owner is not attending Daily Scrum, only developers