PSM I Exam - Question 73


How is management external to the Scrum Team involved in the Daily Scrum?

Show Answer
Correct Answer: B

The Daily Scrum is an event in the Scrum framework that is meant primarily for the development team to discuss their progress towards the Sprint Goal and plan their work for the next 24 hours. Management is not required to attend the Daily Scrum. Its purpose is to allow the developers to quickly and effectively synchronize their activities and create a plan for the day. The involvement of management in this meeting would bypass the self-organizing nature of the Scrum team.

Discussion

3 comments
Sign in to comment
Mi_Windsor
Aug 10, 2023

Why not D? Please explain

yasir_34z
Nov 3, 2023

The question focuses on Daily Scrum, and Product Owner is a representative of the management but he is not required to attend Daily Scrum.

Jyoti1010Option: B
Sep 26, 2023

Daily scrum is attended by the developers only.

ceausorinOption: D
Oct 14, 2023

Why not D?

ficklesena
Oct 19, 2023

Product Owner is not attending Daily Scrum, only developers