PSM II Exam - Question 67


During the Sprint Retrospective, the team is discussing the quality issues that prevented the team from delivering a releasable Increment at the end of the Sprint.

The Development Team does, however, mention that they were able to achieve a high velocity.

What are the best two responses for Steven, their Scrum Master, to take? (Choose two.)

Show Answer
Correct Answer: AD

The primary focus in Scrum should be on delivering a potentially shippable product Increment at the end of each Sprint. While high velocity can be a positive indicator, it is not as important as having working software. Therefore, Steven should stress the value of working software over measured velocity and facilitate a discussion on how to improve the quality to a level high enough for the Increment to be releasable. These actions will help the team align with the fundamental principles of Scrum and ensure they deliver real value.

Discussion

1 comment
Sign in to comment
amogOptions: AD
Mar 9, 2021

Agree on A and D