Question 12

When multiple Scrum Teams are working from the same Product Backlog, also known as scaled Scrum, they must still work in conformance of the Scrum guide.

    Correct Answer: A

    When multiple Scrum Teams are working from the same Product Backlog, they must still work in conformance with the Scrum Guide. The Scrum Guide provides a framework that ensures all teams follow the same basic principles and practices, ensuring consistency and alignment across teams even in a scaled Scrum environment.

Discussion
Mi_WindsorOption: A

A is true

MYAT_T0TOption: A

A is true

lenanguyen89Option: A

A is correct answer

amogOption: A

A is the answer